18
Appendix A: Workshop Process Details
10. Votes were obtained instantaneously and anonymously;
11. Based on the results of the SME votes, the facilitator calculated the average
Likelihood (L) and average Consequence (C) [average = sum of votes /
number of votes] and Risk [L x C] for each event; then categorized their
respective risk ratings. Standard deviation (SD) was than calculated. Draft
results were validated with each SME and any changes made were factored
into the final Top 10 risk list. The Employer Top 10 and Worker Top 10 were
compared with the overall Workshop Results Top 10, respectively;
12. Final results were released to the workshop participants, MLITSD and
relevant HSAs to the sector.